[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126033":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1126033,792,1,"单选题","分包单位施工进度计划应是承包单位施工总进度计划的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基础",false,{"key":16,"text":17,"correct":18},"B","控制范围",true,{"key":20,"text":21,"correct":14},"C","依据",{"key":23,"text":24,"correct":14},"D","组成部分","P249-250 分包工程控制： (1)分包单位的施工进度计划必须依据承包单位的施工进度计划编制。 (2)承包单位应将分包的施工进度计划纳入总进度计划的控制范围。 (3)总、分包之间相互协调，处理好进度执行过程中的相关关系，承包单位应协助分包单位解决施工进度控制中的相关问题。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]