[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126032":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1126032,792,1,"单选题","季度施工进度计划是在年度施工进度计划的基础上，按照（ ）施工原则编制。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分部",false,{"key":16,"text":17,"correct":14},"B","分项",{"key":19,"text":20,"correct":14},"C","顺序",{"key":22,"text":23,"correct":24},"D","均衡",true,"P249-250 计划总工期跨越一个年度以上时，必须根据施工总进度计划的施工顺序，划分出不同年度的施工内容，编制年度施工进度计划，并在此基础上按照均衡施工原则，编制各季度施工进度计划。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]