[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126018":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1126018,792,1,"单选题","合同工期内发生的每笔索赔均应形成完整资料，它是工程（）资料的组成部分。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","竣工",true,{"key":16,"text":17,"correct":18},"B","技术",false,{"key":20,"text":21,"correct":18},"C","合同",{"key":23,"text":24,"correct":18},"D","计量","P214-216 索赔的管理： (1)由于索赔引起费用或工期的增加，往往成为上级主管部门复查的对象。为真实、准确反映索赔情况，承包方应建立、健全工程索赔台账或档案。 (2)索赔台账应反映索赔发生的原因，索赔发生的时间、索赔意向提交时间、索赔结束时间，索赔申请工期和费用，监理工程师审核结果，发包方审批结果等内容。 (3)对合同工期内发生的每笔索赔均应及时登记。工程完工时应形成完整的资料，作为工程竣工资料的组成部分。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]