[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126005":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1126005,792,1,"单选题","经返修或加固处理的分项工程、分部工程，虽然改变外形尺寸但仍能满足( )要求，可按技术处理方案文件和协商文件进行验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","结构安全和使用功能",true,{"key":16,"text":17,"correct":18},"B","结构强度和使用功能",false,{"key":20,"text":21,"correct":18},"C","结构安全和环境保护",{"key":23,"text":24,"correct":18},"D","结构稳定和环境保护","2020版教材P327 经返修或加固处理的分项工程、分部工程，虽然改变外形尺寸但仍能满足结构安全和使用功能要求，可按技术处理方案文件和协商文件进行验收。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]