[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125986":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1125986,792,1,"单选题","箱涵顶进挖土施工，应在（）时间进行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","列车低速运行时",false,{"key":16,"text":17,"correct":18},"B","列车运行间隙",true,{"key":20,"text":21,"correct":14},"C","列车运行时",{"key":23,"text":24,"correct":14},"D","列车减速运行时","2020版教材P321 (3)在列车运行间隙或避开交通高峰期开挖和顶进；列车通过时，严禁挖土作业，人员应撤离开挖面。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]