[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125961":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1125961,792,1,"单选题","关于柔性管道的沟槽回填质量控制，以下说法错误的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","回填前，检查管道有无损伤及变形，有损伤管道应修复或更换",false,{"key":16,"text":17,"correct":14},"B","管内径大于800㎜的柔性管道，回填施工中应在管内设竖向支撑",{"key":19,"text":20,"correct":14},"C","管道回填时间宜在一昼夜中气温最低的时刻，从管道两侧同时回填，同时夯实",{"key":22,"text":23,"correct":24},"D","管道回填从管底基础部位开始到管顶以上0.5m范围内，采用机械或人工回填，管顶0.5m以上部位。可用机械从管道轴线两侧同时回填夯实",true,"2020版教材P297 柔性管道回填施工质量检检查与验收。见原文：回填前，检查管道有无损伤或变形，有损伤的管道应修复或更换，A正确；管内径大于800mm的柔性管道，回填施工时应在管内设竖向支撑，B正确。中小管道应采取防止管道移动措施。管道回填时间宜在一昼夜中气温最低时段，从管道两侧同时回填，同时夯实。C正确；管道回填从管底基础部位开始到管顶以上500mm范围内，必须采用人工回填；管顶500mm以上部位，可用机械从管道轴线两侧同时夯实；每层回填高度应不大于200mm.D选项错误。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]