[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125939":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1125939,792,1,"单选题","喷射混凝土施工时，喷射作业分段、分层进行，喷射顺序( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","由上而下",false,{"key":16,"text":17,"correct":14},"B","由右而左",{"key":19,"text":20,"correct":14},"C","由左而右",{"key":22,"text":23,"correct":24},"D","由下而上",true,"2020版教材P277 4)喷射混凝土施工：喷射作业分段、分层进行，喷射顺序是由下而上。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]