[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125932":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1125932,792,1,"单选题","后张法预应力筋张拉后，孔道( )压浆。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","宜尽早",false,{"key":16,"text":17,"correct":14},"B","不急于",{"key":19,"text":20,"correct":21},"C","应及时",true,{"key":23,"text":24,"correct":14},"D","暂缓","2020版教材P275 （三）压浆与封锚，张拉后，应及时进行孔道压浆。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]