[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125923":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1125923,792,1,"单选题","预应力筋张拉前应根据设计要求对孔道的( )进行实测。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","摩阻损失",true,{"key":16,"text":17,"correct":18},"B","直径",false,{"key":20,"text":21,"correct":18},"C","摩阻力",{"key":23,"text":24,"correct":18},"D","长度","2020版教材P274 预应力筋张拉前应根据设计要求对孔道的摩阻损失进行实测，以便确定张拉力控制应力，并确定预应力筋的理论伸长值。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]