[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125921":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1125921,792,1,"单选题","钻孔灌注桩施工时，为防止塌孔与缩径，通常采取措施之一是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","控制成孔速度",true,{"key":16,"text":17,"correct":18},"B","部分回填黏性土",false,{"key":20,"text":21,"correct":18},"C","全部回填黏性土",{"key":23,"text":24,"correct":18},"D","上下反复提钻扫孔","2020版教材P268 钻孔灌注桩施工时塌孔与缩径产生的原因基本相同，主要是地层复杂、钻进速度过快、护壁泥浆性能差、成孔后放置时间过长没有灌注混凝土等原因所造成。其预防措施是钻（冲）孔灌注桩穿过较厚的砂层、砾石层时，成孔速度应控制在2m\u002Fh以内，泥浆性能主要控制其密度、黏度、含砂率，若孔内自然造浆不能满足要求时，可采用加黏土粉、烧碱、木质素的方法，改善泥浆的性能，通过对泥浆的除砂处理，可控制泥浆的密度和含砂率。没有特殊原因，钢筋骨架安装后应立即灌注混凝土。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]