[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125916":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1125916,792,1,"单选题","日均气温达25℃时，水泥混凝土路面拌合物运输要做到( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","覆盖保温",false,{"key":16,"text":17,"correct":18},"B","用连续搅拌车运送",true,{"key":20,"text":21,"correct":14},"C","装料高度不超过2m",{"key":23,"text":24,"correct":14},"D","确保在水泥混凝土终凝前有充分时间完成路面抹面","2020版教材P261 (二）运输(1)配备足够的运输车辆，总运力应比总拌合能力略有富余，以确保混凝土在规定时间到场。混凝土拌合物从搅拌机出料到铺筑完成时间不能超过规范规定。(2)城镇道路施工中，一般采用混凝土罐车运送。(3)运输车辆要防止漏浆、漏料和离析，夏季烈日、大风、雨天和低温天气远距离运输时，应遮盖混凝土，冬季要保温。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]