[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125909":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1125909,792,1,"单选题","关于城镇道路土路基雨期施工的说法，正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","集中力量，全面开花，快速施工",false,{"key":16,"text":17,"correct":18},"B","坚持当天挖完、填完、压完，不留后患",true,{"key":20,"text":21,"correct":14},"C","填土路基应按2%～4%以上的横坡整平压实",{"key":23,"text":24,"correct":14},"D","因雨翻浆地段，用重型压路机重新压实","2020版教材P262 (二）路基施工(1)对于土路基施工，要有计划地集中力量，组织快速施工，分段开挖，切忌全面开花或挖段过长。(2)挖方地段要留好横坡，做好截水沟。坚持当天挖完、填完、压完，不留后患。因雨翻浆地段，坚决换料重做。(3)填方地段施工，应留2%-3%的横坡整平压实，以防积水。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]