[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125890":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1125890,792,1,"单选题","城镇道路稳定类材料基层雨期施工不宜( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","摊铺段过长",true,{"key":16,"text":17,"correct":18},"B","当日摊铺、当日碾压成活",false,{"key":20,"text":21,"correct":18},"C","未碾压的料层受雨淋后，应进行测试分析，按配合比要求重新搅拌",{"key":23,"text":24,"correct":18},"D","及时开挖排水沟或排水坑，以便尽快排除积水","2020版教材P263 （1）对稳定类材料基层，摊铺段不宜过长，应坚持拌多少、铺多少、压多少、完成多少，当日碾压成活（2）下雨来不及完成时，要尽快碾压，防止雨水渗透。未碾压的料层受雨淋后，应进行测试分析，按配合比要求重新搅拌，及时开挖排水沟或排水坑，以便尽快排除积水",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]