[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125870":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1125870,792,1,"单选题","单位工程、分部工程和分项工程开工前，应对承担施工的负责人或分包方全体人员进行书面技术交底，其执行人为项目( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","负责人",false,{"key":16,"text":17,"correct":14},"B","生产负责人",{"key":19,"text":20,"correct":21},"C","技术负责人",true,{"key":23,"text":24,"correct":14},"D","质量负责人","2020版教材P254 技术交底与培训中（1）单位工程、分部工程和分项工程开工前，项目技术负责人对承担施工的负责人或分包方全体人员进行书面技术交底。技术交底资料应办理签字手续并归档。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]