[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125842":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1125842,792,1,"单选题","施工成本目标控制主要依据之一是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","成本目标",false,{"key":16,"text":17,"correct":14},"B","成本核算",{"key":19,"text":20,"correct":21},"C","成本计划",true,{"key":23,"text":24,"correct":14},"D","成本分析","2020版教材P220 市政公用工程项目施工管理中的施工成本目标控制的依据。可知：施工成本目标控制主要依据四点，（1）工程承包合同，（2）施工成本计划，（3）进度报告，（4）工程变更。施工成本计划是根据项目施工的具体情况指定的施工成本控制方案。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]