[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125839":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1125839,792,1,"单选题","施工项目部实现有效的全过程成本管理的保证和基础是建立健全( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","统计制度",false,{"key":16,"text":17,"correct":18},"B","责任制度",true,{"key":20,"text":21,"correct":14},"C","考核制度",{"key":23,"text":24,"correct":14},"D","会计制度","2020版教材P219 市政公用工程项目施工管理中的施工成本管理。施工项目各项责任制度是实现有效的全过程成本管理的保证和基础。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]