[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125834":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1125834,792,1,"单选题","施工成本分析中，按施工进展进行的成本分析内容，不包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","企业管理费分析",true,{"key":16,"text":17,"correct":18},"B","月(季)度成本分析",false,{"key":20,"text":21,"correct":18},"C","年度成本分析",{"key":23,"text":24,"correct":18},"D","竣工成本分析","2020版教材P224 1. 按施工进展进行的成本分析 包括分部分项工程成本分析、月（季）度成本分析、年度成本分析、竣工成本分析。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]