[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125832":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1125832,792,1,"单选题","发生工程变更时，应由承包人以正式函件首先向()提出索赔申请。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发包方负责人",false,{"key":16,"text":17,"correct":14},"B","业主代表",{"key":19,"text":20,"correct":21},"C","监理工程师",true,{"key":23,"text":24,"correct":14},"D","主管发包方部门","2020版教材P167 市政公用工程项目施工管理中的合同管理。承包方根据施工合同，向监理工程师提出变更申请。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]