[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125830":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1125830,792,1,"单选题","以下选项中属于合同风险分散和转移的措施是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","增设风险合同条款",false,{"key":16,"text":17,"correct":14},"B","加强索赔管理",{"key":19,"text":20,"correct":21},"C","向保险公司投保",true,{"key":23,"text":24,"correct":14},"D","增设保值条款","2020版教材P217 市政公用工程项目施工管理中的风险。风险的分散和转移：①向保险公司投保②向分包商转移部分风险。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]