[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125828":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1125828,792,1,"单选题","索赔证据资料中，不包括()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","索赔金额计算依据",false,{"key":16,"text":17,"correct":14},"B","索赔工期计算依据",{"key":19,"text":20,"correct":14},"C","索赔事件原因",{"key":22,"text":23,"correct":24},"D","项目部组成人员变更",true,"2020版教材P215 市政公用工程项目施工管理中的索赔。索赔的证据资料，包括事件的原因、对其权益影响的资料、索赔的依据，以及其他计算出该事件影响所要求的索赔额和申请延期的天数。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]