[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125827":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1125827,792,1,"单选题","向监理工程师发出索赔意向通知，应在索赔事件发生后()内方为有效。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","14d",false,{"key":16,"text":17,"correct":18},"B","28d",true,{"key":20,"text":21,"correct":14},"C","42d",{"key":23,"text":24,"correct":14},"D","56d","2020版教材P215 市政公用工程项目施工管理中的索赔。合同实施过程中，凡不属于承包方责任导致项目拖延和成本增加事件发生后的28d内，必须以正式函件通知监理工程师。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]