[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125820":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1125820,792,1,"单选题","有效控制工程造价就是要做到()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投资估算>设计概算>施工图预算>竣工结算",true,{"key":16,"text":17,"correct":18},"B","设计概算>投资估算>施工图预算>竣工结算",false,{"key":20,"text":21,"correct":18},"C","竣工结算>施工图预算>设计概算>投资估算",{"key":23,"text":24,"correct":18},"D","投资估算>施工图预算>设计概算>竣工结算","2020版教材P210 工程造价管理的基本内容就是合理确定和有效地控制工程造价，合理确定工程造价就是在建设工程的各个阶段，合理确定投资估算、概算造价、预算造价、合同造价和竣工结算造价，有效控制工程造价也就是在优化建设方案、设计方案的基础上，在建设工程的各个阶段采用适当的方法和措施，把工程造价控制在合理的范围和核定的造价限额以内，就如通常规定的设计概算不得大于投资估算，施工图预算不得大于设计概算，竣工结算不得大于施工图预算。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]