[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125807":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1125807,792,1,"单选题","《城镇道路工程施工与质量验收规范》(CJJ1—2008)规定，水泥混凝土路面在面层混凝土（ ）强度达到设计强度且填缝完成前不得开放交通。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","抗拉",false,{"key":16,"text":17,"correct":14},"B","抗压",{"key":19,"text":20,"correct":21},"C","弯拉",true,{"key":23,"text":24,"correct":14},"D","抗剪","P336 水泥混凝土路面在面层混凝土弯拉强度达到设计强度，且填缝完成前，不得开放交通。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]