[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125799":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1125799,792,1,"单选题","明挖法施工中，下列（）均属于工程监测等级为一级、二级、三级应测项目",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","立体结构竖向偏移",false,{"key":16,"text":17,"correct":14},"B","立体结构应力",{"key":19,"text":20,"correct":21},"C","支撑轴力",true,{"key":23,"text":24,"correct":14},"D","土钉拉力","2020版教材P203 明挖法和盖挖法基坑支护结构和周围岩土体监测项目，A只有在一级和二级中是应测，三级是选测。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]