[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125783":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1125783,792,1,"单选题","水泥混凝土路面在面层混凝土( )，不得开放交通。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","弯拉强度达到设计强度前",false,{"key":16,"text":17,"correct":14},"B","填缝完成前",{"key":19,"text":20,"correct":21},"C","弯拉强度达到设计强度，且填缝完成前",true,{"key":23,"text":24,"correct":14},"D","抗压强度达到设计强度，且填缝完成前","2020版教材P336 水泥混凝土路面在面层混凝土弯拉强度达到设计强度且填缝完成前不得开放交通。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]