[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125775":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1125775,792,1,"单选题","依附于城市道路的各种管线、杆线等设施的建设，应坚持( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先地下、后地上的施工原则，与城市道路同步建设",true,{"key":16,"text":17,"correct":18},"B","先地下、后地上的施工原则，与城市道路异步建设",false,{"key":20,"text":21,"correct":18},"C","先地上、后地下的施工原则，与城市道路同步建设",{"key":23,"text":24,"correct":18},"D","先地上、后地下的施工原则，与城市道路异步建设","2020版教材P334 城市供水、排水、燃气、热力、供电、通信、消防等依附于城市道路的各种管线、杆线等设施的建设计划，应与城市道路发展规划和年度建设计划相协调，坚持先地下、后地上的施工原则，与城市道路同步建设。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]