[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125767":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1125767,792,1,"单选题","当市政公用工程平面布置改变超过图上面积（ ）时，不宜在原施工图上修改和补充，应重新绘制竣工图。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1\u002F2",false,{"key":16,"text":17,"correct":14},"B","2\u002F3",{"key":19,"text":20,"correct":14},"C","3\u002F4",{"key":22,"text":23,"correct":24},"D","1\u002F3",true,"P196-199 当平面布置改变超过图上面积1\u002F3 时，不宜在原施工图上修改和补充，应重新绘制竣工图。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]