[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125631":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1125631,792,1,"单选题","沥青面层施工过程中，下列压路机驾驶员的行为中正确的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","在未碾压成型路面上驾驶压路机转向、掉头",false,{"key":16,"text":17,"correct":14},"B","施工间歇期间，将压路机停放在未成型路面上",{"key":19,"text":20,"correct":14},"C","工休期间，将压路机停放在刚成型路面上",{"key":22,"text":23,"correct":24},"D","碾压过程中，驾驶压路机缓慢倒退碾压路面",true,"2021\u002F2020版教材P21页 (8)压路机不得在未碾压成型路段上转向、掉头、加水或停留。在当天成型的路面上，不得停放各种机械设备或车辆，不得散落矿料、油料及杂物。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]