[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125610":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1125610,792,1,"单选题","下面关于水泥稳定土说法错误的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","宜在春末和气温较高季节施工，施工期的日最低气温应在5°C以上",false,{"key":16,"text":17,"correct":14},"B","下雨时停止施工，已摊铺的水泥稳定土结构层应尽快碾压密实",{"key":19,"text":20,"correct":21},"C","应在混合料处于最佳含水量+5%时进行碾压",true,{"key":23,"text":24,"correct":14},"D","压实成活后立即洒水养护，保持湿润","2021\u002F2020版教材P17页 (2)摊铺好的稳定土类混合料应当天碾压成型，碾压时的含水量宜在最佳含水量的±2%范围内。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]