[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125579":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1125579,792,1,"单选题","某道路填方路基含一座φ1000管涵，局部原地面坡度达1：4，合适的施工方法是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","地面坡度1:4处修筑台阶",true,{"key":16,"text":17,"correct":18},"B","当填土达一定长度(100m)时，只检查平整度合格后即开始碾压",false,{"key":20,"text":21,"correct":18},"C","在管涵处，待其顶面覆土达200mm时，用压路机碾压",{"key":23,"text":24,"correct":18},"D","路基填筑最后的碾压选用8t级压路机","2021\u002F2020版教材P10页 (3)填方段内应事先找平，当地面坡度陡于1:5时，需修成台阶形式，每层台阶高度不宜大于300mm，宽度不应小于1.0m。(5)碾压前检查铺筑土层的宽度与厚度，合格后即可碾压，碾压“先轻后重”，最后碾压应采用不小于12t级的压路机。(6)填方高度内的管涵顶面填土500mm以上才能用压路机碾压。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]