[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125578":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1125578,792,1,"单选题","填土(方)路基，填方段内应事先找平，当地面坡度陡于( )时，需修成台阶形式。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1:4",false,{"key":16,"text":17,"correct":14},"B","1:6",{"key":19,"text":20,"correct":21},"C","1:5",true,{"key":23,"text":24,"correct":14},"D","1:3","2021\u002F2020版教材P10页 （3）、填方段应事先找平，当地面坡度陡于1:5时，需修成台阶形式，每层台阶高度不宜大于300mm，每级台阶宽度不得小于1.0m.",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]