[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125573":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1125573,792,1,"单选题","HDPE膜不得在（）季施工。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","春",false,{"key":16,"text":17,"correct":14},"B","夏",{"key":19,"text":20,"correct":14},"C","秋",{"key":22,"text":23,"correct":24},"D","冬",true,"P175-183 根据焊接能力合理安排每天铺设HDPE膜的数量。在恶劣天气来临前，减少展开HDPE膜的数量，做到能焊多少铺多少。冬期严禁铺设。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]