[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125536":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1125536,792,1,"单选题","在实施焊接前，应根据焊接工艺试验结果编写焊接工艺方案，方案内容不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","焊接材料",false,{"key":16,"text":17,"correct":18},"B","焊接单位",true,{"key":20,"text":21,"correct":14},"C","焊接方法",{"key":23,"text":24,"correct":14},"D","检验方法","P145-151 在实施焊接前，应根据焊接工艺试验结果编写焊接工艺方案，方案应包括以下主要内容： ①管材、板材性能和焊接材料； ②焊接方法； ③坡口形式及制作方法； ④焊接结构形式及外形尺寸； ⑤焊接接头的组对要求及允许偏差； ⑥焊接电流的选择； ⑦焊接质量保证措施； ⑧检验方法及合格标准。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]