[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125514":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1125514,792,1,"单选题","按燃气流动方向，安装在管道最高点和每个阀门之前的附属设备是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","放散管",true,{"key":16,"text":17,"correct":18},"B","排水器",false,{"key":20,"text":21,"correct":18},"C","补偿器",{"key":23,"text":24,"correct":18},"D","绝缘法兰","2021\u002F2020版教材P173 放散管安装在最高点和每个阀门之前（按燃气流动方向）。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]