[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125505":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1125505,792,1,"单选题","聚乙烯双壁波纹管隐蔽竣工验收合格后沟槽回填时不正确的施工方法是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","从管底基础部位开始到管顶以上0.5m范围内，必须人工回填，严禁用机械推土回填",false,{"key":16,"text":17,"correct":14},"B","回填前应排除沟槽积水，不得回填淤泥、有机物及冻土",{"key":19,"text":20,"correct":14},"C","回填土的含水量，应按回填材料和采用的压实工具控制在最佳含水量附近",{"key":22,"text":23,"correct":24},"D","为减少土方倒运，闭水试验合格段先回填至管顶部位，待另一段开挖时再回填管顶以上部位",true,"2021\u002F2020版教材P167 2.沟槽回填(1)不得采用冻土、垃圾、木材及软性物质回填。管道两侧及管顶以上0.5m内的回填土，不得含有碎石、砖块等杂物，且不得采用灰土回填。距管顶0.5m以上的回填土中的石块不得多于10%、直径不得大于0.1m，且均匀分布。(2)沟槽的支撑应在管道两侧及管顶以上0.5m回填完毕并压实后，在保证安全的情况下进行拆除，并应采用细砂填实缝隙。(3)沟槽回填时，应先回填管底局部悬空部位，再回填管顶两侧。(4)回填土应分层压实，每层虚铺厚度宜为0.2-0.3m，管道两及管顶以上0.5m内的回填土必须采用人工压实，管顶0.5m以上的回填土可采用小型机械压实，每层虚铺厚度宜为0.25-0.4m。(5)回填土压实后，应分层检查密实度，并做好回填记录。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]