[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125452":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1125452,792,1,"单选题","有补偿器装置的热力管道，在补偿器安装前，管道和( )不得进行固定连接。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","导向支架",false,{"key":16,"text":17,"correct":14},"B","悬吊支架",{"key":19,"text":20,"correct":21},"C","固定支架",true,{"key":23,"text":24,"correct":14},"D","滚动支架","2021\u002F2020版教材P152 固定支架安装应符合下列规定：(2)有补偿器的管段，在补偿器安装前，管道和固定支架之间不得进行固定。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]