[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125401":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1125401,792,1,"单选题","关于沟槽开挖下列说法中错误的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","人工开挖沟槽的挖深较大时，应按每层3m进行分层开挖",true,{"key":16,"text":17,"correct":18},"B","机械挖槽时，沟槽分层深度按机械性能确定",false,{"key":20,"text":21,"correct":18},"C","槽底原状地基土不得扰动",{"key":23,"text":24,"correct":18},"D","槽底不得受水浸泡或受冻","2021\u002F2020版教材P134 人工开挖沟槽的槽深超过3m时应分层开挖，每层的深度不超过2m。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]