[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125389":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1125389,792,1,"单选题","沉井封底前自沉速率应小于( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10mm／8h",true,{"key":16,"text":17,"correct":18},"B","15mm／8h",false,{"key":20,"text":21,"correct":18},"C","20mm／8h",{"key":23,"text":24,"correct":18},"D","25mm／8h","P127-130 终沉时，每小时测一次，严格控制超沉，沉井封底前自沉速率应小于10mm\u002F8h。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]