[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125388":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1125388,792,1,"单选题","为严格控制超沉，沉井终沉时，沉井的标高、轴线位移至少( )测量一次。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1h",true,{"key":16,"text":17,"correct":18},"B","2h",false,{"key":20,"text":21,"correct":18},"C","4h",{"key":23,"text":24,"correct":18},"D","6h","P127-130 终沉时,每小时测一次,严格控制超沉,沉井封底前自沉速率应小于10mm\u002F8h。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]