[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125386":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1125386,792,1,"单选题","分节制作、分次下沉的沉井，后续各节的模板底部应距地面不小于（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.9m",false,{"key":16,"text":17,"correct":18},"B","1.0m",true,{"key":20,"text":21,"correct":14},"C","0.8m",{"key":23,"text":24,"correct":14},"D","0.7m","P127-130 分节制作、分次下沉的沉井,前次下沉后进行后续接高施工: (1)应验算接高后稳定系数等,并应及时检查沉井的沉降变化情况,严禁在接高施工过程中沉井发生倾斜和突然下沉。 (2)后续各节的模板不应支撑于地面上,模板底部应距地面不小于1m，搭设外排脚手架应与模板脱开。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]