[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125372":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1125372,792,1,"单选题","对大中型水池，做满水试验进行外观观测时，要求( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","充水至池壁底部的施工缝以上，检查底板的抗渗质量",true,{"key":16,"text":17,"correct":18},"B","充水至设计水深的1\u002F3处，检查池壁四周及池底的抗渗质量",false,{"key":20,"text":21,"correct":18},"C","充水至池底一定高度后，检查池底部抗渗质量",{"key":23,"text":24,"correct":18},"D","必须充水至设计水深的1\u002F2处，检查池底的抗渗质量","2021\u002F2020版教材P132 满水试验：可先注水至池壁底部施工缝以上，检查地板抗渗质量。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]