[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125368":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1125368,792,1,"单选题","构筑物水池满水试验程序应为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","水池注水→水池内水位观测→蒸发量测定→整理试验结论",false,{"key":16,"text":17,"correct":18},"B","试验准备→水池注水→水池内水位观测→蒸发量测定→整理试验结论",true,{"key":20,"text":21,"correct":14},"C","试验准备→水池注水→蒸发量测定，同时测水池内水位→整理试验结论",{"key":23,"text":24,"correct":14},"D","根据有关资料→水池注水→蒸发量测定→水池内水位观测→整理试验结论","2021\u002F2020版教材P131 试验流程：试验准备→水池注水→水池内水位观测→蒸发量测定→整理试验结论。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]