[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125364":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1125364,792,1,"单选题","沉井下沉时工人6小时换班一次，沉井的标高、轴线位移至少( )测量一次。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1h",false,{"key":16,"text":17,"correct":14},"B","2h",{"key":19,"text":20,"correct":14},"C","4h",{"key":22,"text":23,"correct":24},"D","6h",true,"2021\u002F2020版教材P129 下沉时高程、轴线位移每班至少测量一次，每次下沉稳定后应进行高差和中心位移量的计算。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]