[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125358":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1125358,792,1,"单选题","分节制作、分次下沉的沉井，后续各节的模板底部应距地面不小于( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.9m",false,{"key":16,"text":17,"correct":18},"B","1m",true,{"key":20,"text":21,"correct":14},"C","0.8m",{"key":23,"text":24,"correct":14},"D","0.7m","2021\u002F2020版教材P128 分节制作沉井：后续各节的模板不应支撑于地面上，模板底部应距地面不小于1m。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]