[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125348":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1125348,792,1,"单选题","整体式现浇钢筋混凝土池体结构施工流程中，不含( )工序。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","土方开挖及地基处理",false,{"key":16,"text":17,"correct":18},"B","中心支柱浇筑",true,{"key":20,"text":21,"correct":14},"C","底板浇筑",{"key":23,"text":24,"correct":14},"D","顶板浇筑","2021\u002F2020版教材P124 整体式现浇钢筋混凝土水池工艺流程：测量定位→土方开挖及地基处理→垫层施工→防水层施工→底板浇筑→池壁及顶板支撑柱浇筑→顶板浇筑→功能性试验。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]