[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125317":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1125317,792,1,"单选题","基坑开挖方案应根据（）确定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","支护结构设计、降排水要求",true,{"key":16,"text":17,"correct":18},"B","基坑平面尺寸、深度",false,{"key":20,"text":21,"correct":18},"C","基坑深度、周边环境要求",{"key":23,"text":24,"correct":18},"D","基坑深度、降排水要求","P99-104 基坑开挖应根据支护结构设计、降排水要求，确定开挖方案。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]