[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125315":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1125315,792,1,"单选题","地铁基坑内支撑围护结构的挡土应力传递路径是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","围檩→支撑→围护墙",false,{"key":16,"text":17,"correct":14},"B","围护墙→支撑→围檩",{"key":19,"text":20,"correct":21},"C","围护墙→围檩→支撑",true,{"key":23,"text":24,"correct":14},"D","支撑→围护墙→围檩","P93-99 支撑结构挡土的应力传递路径是围护(桩)墙→围檩(冠梁)→支撑。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]