[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125307":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1125307,792,1,"单选题","管棚超前支护是为安全开挖预先提供增强地层承载力的（）支护方法。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","临时",true,{"key":16,"text":17,"correct":18},"B","永久",false,{"key":20,"text":21,"correct":18},"C","强力",{"key":23,"text":24,"correct":18},"D","附加","P115-116 管棚法是为防止隧道开挖引起地表下沉和围岩松动，在开挖掘进前沿开挖工作面的上半断面周边按设计打入厚壁钢管，在地层中构筑的临时承载棚防护下，为安全开挖预先提供增强地层承载力的临时支护方法，与小导管注浆法相对应，通常又称为大管棚超前支护法。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]