[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125289":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1125289,792,1,"单选题","浅埋暗挖法施工时，处于砂砾地层，并穿越既有铁路，宜采用的辅助施工方法是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","地面砂浆锚杆",false,{"key":16,"text":17,"correct":14},"B","小导管注浆加固",{"key":19,"text":20,"correct":21},"C","管棚超前支护",true,{"key":23,"text":24,"correct":14},"D","降低地下水位","2021\u002F2020版教材P115 (二）适用条件(1)适用于软弱地层和特殊困难地段，如极破碎岩体、塌方体、砂土质地层、强膨胀性地层、强流变性地层、裂隙发育岩体、断层破砗带、浅埋大偏压等围岩，并对地层变形有严格要求的工程。(2)通常，在下列施工场合应考虑采用管栅进行超前支护:1)穿越铁路修建地下工程；2)穿越地下和地面结构物修建地下工程；3)修建大断面地下工程；4)隧道洞口段施工；5)通过断层破碎带等特殊地层；6)特殊地段，如大跨度地铁车站、重要文物护区、河底、海底的地下工程施工等。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]