[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125279":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1125279,792,1,"单选题","关于喷锚暗挖法二衬混凝土施工的说法，错误的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","可采用补偿收缩混凝土",false,{"key":16,"text":17,"correct":14},"B","可采用组合钢模板和钢模板台车两种模板体系",{"key":19,"text":20,"correct":14},"C","采用泵送人模浇筑",{"key":22,"text":23,"correct":24},"D","混凝土应两侧对称、水平浇筑，可设置水平和倾斜接缝",true,"2021\u002F2020版教材P113 二衬混凝土施工要求如下：(1)二衬采用的补偿收缩混凝土，应具有良好的抗裂性能，主体结构防水混凝土在工程结构中不但承担防水作用，还要和钢筋一起承担结构受力作用。(2)二衬混凝土浇筑应采用组合钢模板和模板台车两种模板体系。应对模板及支撑结构进行验算，以保证其具有足够的强度、刚度和稳定性，防止发生变形和下沉。模板接缝要拼贴平整、严密，避免漏浆。(3)混凝土浇筑采用泵送入模浇筑，两侧边墙采用插入式振捣器振捣，底部采用附着式振动器振捣。混凝土浇筑应连续进行，两侧对称，水平浇筑，不得出现水平和倾斜接缝；如混凝土浇筑因故中断，则必须采取措施对两次浇筑混凝土界面进行处理，以满足防水要求。综上所述可知D选项错误。其他三个选项均为喷锚暗挖法二衬混凝土施工的正确做法。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]